Misae Solar I Energy Construction Project

What does saving 440,000 tons of CO 2 emissions from entering the atmosphere look like?

¾º²Ê×ãÇòapp Builds Ninth Solar Project in Texas

The 326 MWdc Misae Solar I project, located in Childress, Texas, was ¾º²Ê×ãÇòapp's ninth solar project in the state. It generates enough clean energy to power nearly 60,000 houses per year.

¾º²Ê×ãÇòapp connected the solar farm to the grid through the construction of a greenfield 34.5/345kV substation with two 34.5/345kV main power transformers, three 345kV vertical break switches, one 345kV breaker, six 34.5kV feeder breakers, many 34.5kV hook stick and vertical break switches, as well as all metering and protection equipment.Ìý

Strong coordination and collaboration proved to be key to successful schedule execution on this project. The continuous interface between ¾º²Ê×ãÇòapp and the transmission service provider and utility off-taker allowed ¾º²Ê×ãÇòapp to execute the necessary upgrades required to meet the solar project schedule.ÌýFamiliarity with ERCOT processes and dedication to clear and consistent communication from start to finish were the differentiating factors.Ìý